Labor costs are one of the most significant expenses in any construction project. However, accurately estimating and calculating construction labor costs is easier said than done. With so many factors to consider, it's no wonder that this task can be overwhelming, especially for those new to the construction industry.
If you're feeling anxious or uncertain about approximating and quantifying construction labor costs, you've come to the right place. In this article, we'll guide you through the process step-by-step, providing you with practical insights, and real-world examples that will help you gain confidence and make informed decisions.
Construction labor costs are the lifeblood of any building project, the very essence of what it takes to turn a set of plans into a tangible structure. It's the hard work, the sweat, the laborious hours spent erecting walls, pouring concrete, and hammering nails that transform a mere idea into a physical reality.
But the cost of that labor is not just measured in hours or dollars. Labor burden is the cost of skilled workers who have spent years honing their craft, of apprentices learning on the job, of equipment and tools needed to get the construction job done right. It's the cost of benefits, insurance, taxes, permits, safety equipment, and training.
That said, several factors contribute to the cost of labor in a construction project. They include:
Let's say you're building a new house, and you need to hire an electrician to install wiring and electrical fixtures. If you hire an experienced electrician who charges a base rate of $40 per hour, and the project takes 200 hours to complete, the total labor cost for the electrician would be $8,000. However, if you hire an apprentice electrician who charges a base rate of $20 per hour, the total labor cost for the same project would be $4,000.
Let's use the same example of hiring an electrician. If the electrician you hire is an employee of your company, you'll need to factor in additional costs such as health insurance, retirement contributions, and payroll taxes. Let's say these direct costs add up to 30% of the electrician's hourly wage. In this case, the total labor cost for the experienced electrician would be $10,400 ($8,000 in wages plus $2,400 in benefits and payroll taxes).
Suppose you need to hire a crane operator to lift heavy materials onto the roof of a building. In this case, you'll need to find a crane operator who is trained and certified to operate the specific type of crane you'll be using. If you hire a crane operator who already has the required training and certification, the labor cost will be lower than if you need to train a new operator from scratch.
Let's say you're building a new commercial kitchen, and you need to install a range hood and exhaust system. If you already own the necessary tools and equipment to install the system, the labor cost will be lower than if you need to rent or purchase the tools and equipment.
Suppose you're working on a job site that requires work outside of normal business hours. If you need overtime rates, the worker’s compensation will be higher than if you only need to pay regular hourly rates. Similarly, if construction companies need to pay shift differentials for work done on weekends or holidays, the labor cost will be higher than if all work is done during normal business hours.
Determining accurate labor cost estimates is crucial for ensuring the success of your projects. Failing to do so could result in overestimating or underestimating project costs, leading to delays, cost overruns, and dissatisfied stakeholders. To ascertain labor expenses for a construction project, follow these steps:
Let's say you're constructing a new residential building. The scope of work might include tasks such as site preparation, foundation work, framing, electrical, plumbing, HVAC, roofing, and finishing work.
If we focus on the electrical work, we might break it down into tasks such as installing the electrical panel, running electrical conduit and wires, installing light fixtures, and mounting electrical outlets.
For assembling the electrical panel, you might estimate that it will take one electrician 4 hours to complete the task. For running electrical conduit and wires, you might approximate that it will take a team of two electricians 40 hours to wrap up. For installing light fixtures, you might project that it will take one electrician 8 hours to finish the task. And for mounting electrical outlets, you might estimate that it will take a team of two electricians 20 hours to complete.
Let's say you have two categories of workers for electrical work: electricians and electrical helpers. You might project that electricians will earn $40 per hour and electrical helpers will earn $25 per hour.
Offering benefits like health care and retirement plans could increase labor costs by as much as 25%. Additionally, if the project timeline is tight, you may need to factor in overtime, which could add another 50% to the labor costs.
Do you want to simplify your projects and reduce unexpected expenses? Here’s how:
By analyzing historical data from previous projects, you can determine the time requirements and actual costs for your current project. This approach provides you with a better understanding of your project's requirements hence accurate estimates. Don't rely on guesswork when you can use data to get accurate estimations.
If you’re a general contractor, your team members or subcontractors have valuable expertise that can help you estimate labor costs more precisely. By collaborating with your team, you can get a better understanding of the project's complexity and requirements. For example, if a colleague has worked on a similar project, they can provide you with insights into how long specific tasks may take to complete.
Experienced and skilled construction workers may complete jobs faster and more efficiently, reducing the overall labor costs. On the other hand, less experienced employees may require more time to complete the same tasks, leading to higher labor costs.
Several construction management tools are available to assist you in accurate time tracking, scheduling management, and estimating labor costs. Project management software is a good example of such a tool. It allows you to track specific job time and estimate labor costs based on that time, streamlining the estimation process and removing the need for guesswork.
Now that you know how to estimate and calculate construction labor costs accurately, it's time to put this knowledge into practice. By factoring in all the variables, such as worker productivity, overtime, and labor laws, you can optimize your labor costs and increase your profit margins. So, go ahead and apply these strategies and best practices to your next construction project.
Plus, you know how costly construction mistakes can be. They slow down progress, lead to rework, and ultimately, erode profitability. That's why you need a solution that helps you stay on track and avoid risk. And lucky for you, our automated risk analysis platform empowers your team to proactively prevent critical path delays and gain real-time financial insights into your project's progress. No more wasted time or money on fixing mistakes and reworking projects.
Discover the transformative power of our solutions and experience a new level of efficiency and productivity.
5/10/21
Team Spotlight
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat.